According to The Times of India, several Chennai Metro construction sites are moving toward milestones that could ease road disruption in the city over the next two years. Barricades at Luz Junction, Panagal Park, Greenways Road and Lighthouse are expected to come down in phases, though the dates vary by site.

Thirumayilai (Luz Junction)

The Thirumayilai interchange station, where Corridors 3 and 4 intersect, is now targeted for completion by December 2028. Engineers found a large metro water pipeline while building the station's diaphragm wall, leaving part of the wall unfinished. Excavation inside the station box cannot start until the outer walls are finished, and a traffic diversion is needed to shift the utility. A metro rail official said the Corridor 4 portion of the station box would be excavated after the wall is complete.

Two tunnel boring machines have crossed Thirumayilai from Lighthouse and are approaching Alwarpet on Corridor 4, while another is tunnelling from RK Salai towards Mandaveli on Corridor 3. Work had also stalled earlier because shops at the site could not be vacated for nearly a year.

Lighthouse

According to The Times of India, Lighthouse station on Corridor 4 may not be ready before March 2028. Track-laying has begun inside the tunnels, and work on the entry and exit structures is under way. Because Thirumayilai may not be ready in time, Chennai Metro Rail Ltd (CMRL) is exploring whether Corridor 4 services could start initially through Thirumayilai.

Greenways Road

The Greenways Road station may be ready by August 2027, but its opening will depend on other stations along the corridor, particularly Thirumayilai, Indira Nagar and Taramani. A CMRL official said trains cannot run through this stretch without the adjoining stations.

Panagal Park

CMRL plans to remove the barricades around Panagal Park by January 2027, once tunnelling from the park towards Boat Club is complete. Tunnelling is expected to finish by the end of December. Only barricades around the park itself will remain. The station beneath the park is expected to be ready by mid-2027. Once the Vadapalani to Panagal Park stretch opens, commuters from Poonamallee and Porur could travel directly to T Nagar by metro.