Infobae México reports that construction of the stations and shafts for the extension of Line 12 of the Mexico City Metro has begun in Mexico City. The phase started on November 20, according to the publisher. Staff from the Secretaría de Obras y Servicios (Sobse) are working together with Metro CDMX personnel on the structures and shafts that will form part of the route.
New stations on the Golden Line
The new stations are Valentín Campa, Álvaro Obregón and Observatorio. According to Infobae México, the underground works stood at 28% at Valentín Campa and 30% at Álvaro Obregón as of July 21, 2026. At Álvaro Obregón, crews were building secondary tunnels and platform walls.
Once the tunnel construction is complete, the work will focus on the stations, pedestrian access and the shafts that will provide ventilation and allow electromechanical equipment to be brought in for track installation.
Timeline and project details
According to Infobae México, Andrés Lajous said the extension between Mixcoac and Observatorio will be completed in 2028. The aim is to link the Golden Line with Line 1 and the Mexico-Toluca Interurban Train. The new section had previously been planned to open in 2029.
- The project includes 4.6 kilometers of underground track and three stations.
- The investment is 11,000 million pesos, financed by the Fondo Nacional de Infraestructura.
- The route will connect the boroughs of Álvaro Obregón and Miguel Hidalgo.
Challenging ground conditions
Infobae México states that subsoil conditions forced a slower excavation pace to avoid risks to the tunnel and to surface buildings. In some areas, progress was only about three meters per month. President Claudia Sheinbaum said there were periods when excavation advanced close to one centimeter per month. Parts of the Álvaro Obregón area were former open-pit mines filled with rubble and low-strength materials.
Observatorio terminal and upcoming works
The Observatorio terminal will have five tracks and two underground platforms. According to the same report, it will connect with Line 1, the Mexico-Toluca Interurban Train and the Terminal de Autobuses del Poniente. The tunnel toward Observatorio is reported to be complete, while work continues at the intermediate stations and the terminal.
A tender for civil and complementary works at Observatorio was published in September. Avenida Sur 122 will be affected because the train workshop area will be located there. Workshop activities are planned for December 2026, once the tender result is known, according to Infobae México.