According to g1 Rio de Janeiro, work on the future Gávea metro station in Rio de Janeiro has entered a new phase with the installation of tracks. The station, on Line 4 in the South Zone, is expected to be completed by mid-2028, according to the project schedule reported by the outlet.
A deep station reached only by lifts
The Gávea station will sit about 57 metres below the surface, making it the deepest station in the city's metro network. Passengers will reach the platform by lifts rather than escalators, which is different from the other stations in the system.
The work has reached 40% completion. Line 4 links Ipanema in the South Zone with Barra da Tijuca in the West Zone. Construction had been paused for about ten years and resumed in April 2025.
Track installation begins
On the Thursday before the report, those responsible for the project started laying the tracks, described by g1 Rio de Janeiro as the third phase since work resumed. Earlier stages included draining the water that had flooded the underground structures and blasting and excavating rock.
The new stage includes preparing the floor, building the drainage system, pouring the concrete base and placing the sleepers and rails. According to the engineers in charge, this work should continue until April 2027.
Funding and expected passenger numbers
According to the State Government, the station is expected to serve about 20,000 passengers a day. The investment set out in the agreement that made the resumption possible is R$ 697 million: R$ 600 million from MetrôRio and R$ 97 million from the state government.
The state secretary for Transport and Urban Mobility, Priscila Sakalem, said the work is on schedule and budget. She also said the state government included its R$ 97 million commitment in the department's budget for 2027, and that no extra funds have been requested so far.
Background
Work on the station began in 2010 as part of preparations for the 2016 Olympic Games, but it was not ready in time, and Line 4 opened without it. Construction was halted in 2015 amid investigations into irregularities on the line. According to g1 Rio de Janeiro, the state audit court (TCE-RJ) estimated a loss of R$ 3.7 billion linked to those irregularities in a 2021 survey.
Before the work stopped, two deep shafts of about 50 metres had been excavated. To reduce the risk of collapse, engineers flooded the shafts and tunnels in January 2018. An agreement approved by TCE-RJ in 2024 enabled the restart and extended the line's concession to 2048.