Bengaluru's Namma Metro is working towards opening the 19-km Phase 2A Blue Line corridor by mid-2027, according to New Indian Express. Bengaluru Development Minister Krishna Byre Gowda inspected a trial run on the KR Puram to Central Silk Board stretch on a Tuesday and gave the timeline.

Corridor and trial run

The corridor has 13 stations and is intended to offer a major transport option along the congested Outer Ring Road (ORR), where several companies employ around 12 lakh people. The current trial run runs from KR Puram towards Mahadevapura and covers four stations. According to the minister, more stations will be added in the coming weeks, with four more stations planned for next month.

Signalling and certification

The minister said the automatic signalling system is expected to be completed by January. Mandatory safety certification would follow after February. The overall testing and certification process is expected to take around eight months.

Wider Blue Line and funding

The government wants the entire 58.2-km Blue Line, from Central Silk Board to KIA via KR Puram and Hebbal, completed within 18 months. The project has an estimated cost of Rs 20,000 crore. Officials have been directed to speed up Phase 2B, particularly the KR Puram to Hebbal stretch.

According to the minister, the state bears loan repayments and supports BMRCL's operational losses. A weaker rupee has increased the repayment burden, which the minister said adds nearly 30% to the loan burden. The government says it is making budget provisions and releasing funds as required.

Finances and fares

The minister said ticket revenue does not cover operating costs. Including depreciation, BMRCL records an annual loss of around Rs 700 crore, while an operating surplus of around Rs 60 crore is estimated when depreciation is excluded. Blue Line operations are expected to raise expenditure. He clarified that no decision has been taken on increasing Metro fares.

Other matters mentioned include the proposed Red Line, which has not yet received central approval, and a proposed double-decker road and Metro corridor from Sarjapur to St John's through Iblur Junction.