A technical fault in the internal power supply of a Pune Metro train disrupted services on the Vanaz-Ramwadi corridor, known as Line 2, on a Sunday, according to Hindustan Times. The incident affected Pune's metro network near Yerawada station.

What happened

According to Hindustan Times, the fault occurred at around 11.38 am on a train travelling from Ramwadi towards Vanaz. The affected train, called a rake in the report, developed the problem near Yerawada metro station and was taken out of service for inspection.

The operator then ran trains on a single line between RTO and Ramwadi, starting at 11.55 am, to limit the impact on other services. Line 2 was reported to be operating normally again at about 1.35 pm, after nearly two hours of disruption.

Cause, according to Pune Metro

Pune Metro officials said the fault was confined to the train's internal power supply system. It did not involve the overhead traction line or the corridor's main electricity supply. The technical team moved the train to Ramwadi metro station, where it was parked at around 1.30 pm.

Chandrasekhar Tambvekar, public relations officer of Pune Metro, said the problem was different from a traction power failure, which could affect train movement across a larger section of the network. He said the issue was resolved by 1.30 pm.

Impact on passengers

Pune Metro said the disruption caused a delay of about two minutes for passengers. The impact was described as relatively limited because the incident happened on a Sunday, when ridership is usually lower. Services continued to run, although the affected stretch operated on a single line.

Passengers quoted in the report described more significant problems. Meera Awale said commuters were asked to get off and use the stairs during the disruption, and she called for better guidance during such situations. She also asked whether ticketing and passenger information systems had been updated after tickets were issued. Rohit Deshmukh said he had to alight at an intermediate station while travelling from District Court towards Pune, wait about 20 minutes, and board another train.

Context

The report notes that the incident came after earlier technical disruptions on the Pune Metro network involving traction power and electrical infrastructure. Officials said this fault was limited to a single train and did not affect the corridor's overhead power supply. The article adds that the reliability of rolling stock and preventive maintenance is under scrutiny as ridership grows.