According to g1 Rio de Janeiro, work on the Gávea metro station in Rio de Janeiro has entered a new phase, with the installation of track on the permanent way now underway. The station is on Line 4, in the South Zone of the city.
The state government announced that track installation started after more than 28 thousand tonnes of rock were removed while the tunnel linking the station to the São Conrado section was excavated. State Secretary of Transport and Urban Mobility Priscila Sakalem visited the construction site on the same day.
What is being built
The government forecasts that the station will open in 2028 and expects it to serve about 20 thousand passengers a day. At 57 metres deep, it will be the deepest station in Rio's metro system.
Work currently focuses on three fronts:
- widening excavations to build the station;
- installing an electrical substation;
- installing the permanent way that will allow trains to run.
The station is being built in two parallel shafts about 50 metres deep. The tunnel to São Conrado is almost fully excavated, and work now centres on enlarging sections to hold the station structure. A separate underground area for electrical equipment, generators and switchboards is also planned, with dimensions similar to a three-storey building.
Track installation timeline
Track laying began on the stretch linking the station to São Conrado. The steps include cleaning the floor, installing drainage to collect seepage water, pouring the concrete base, and later placing sleepers and rails. According to the technical explanation given during the visit, this stage should continue until April 2027.
Background
The Gávea station is part of the Line 4 expansion, which links Ipanema in the South Zone with Barra da Tijuca in the West Zone. Works began in 2010 as part of mobility projects for the 2016 Olympic Games, but the station was not ready in time. Construction was halted between 2015 and 2016 amid investigations into irregularities. Works were officially resumed in April 2025 under an agreement approved by the state audit court TCE-RJ in 2024.
The governor-elect of Rio, Douglas Ruas, said in a statement that metro expansion will be a priority for his administration. He cited the expansion of Lines 2 and 4 and a project for Line 3, with partnerships to be sought with the federal government. The government gives July 2028 as the completion date for the works.