In São Paulo, the Subprefeitura de Pinheiros has authorized the Metrô de São Paulo to temporarily occupy part of a public area in front of number 144 of Rua Medeiros de Albuquerque, in Vila Madalena, according to Diário do Transporte. The area will host a construction site and a support point for the revitalization and accessibility works at Beco do Batman, a street known for its urban murals.
What the authorization covers
The permit remains valid until the works are finished. According to Diário do Transporte, it does not set a delivery date. The Companhia do Metropolitano is responsible for the costs of the site and for returning the public area in usable condition at the end.
The wider project, announced by the city hall, includes sidewalk reforms to improve pedestrian circulation, adjustments to the cobblestone paving while keeping the street's appearance, new street furniture and landscaping, a lookout point, and six rain gardens. These gardens are planted areas meant to absorb part of the rainwater running down the street and ease drainage. The site lies along the route of the Rio Verde, which is now channelled.
Progress and budget
In May, the city administration said work would begin with drainage and expected about five months of interventions. At a meeting of the Conselho Participativo Municipal de Pinheiros, a representative of the Subprefeitura reported that the responsible company had been replaced and that paving stones on the main street had been removed and relaid.
According to Diário do Transporte, municipal documents give different pictures of progress. A partial accounts report for the Fundo de Desenvolvimento Urbano still listed the revitalization and accessibility item on Rua Gonçalo Afonso as under tender. The proposal submitted to the fund in November shows R$ 600 thousand for this item in 2026, compared with R$ 853.7 thousand in the previous plan. The authorization does not fix the total cost of the project.
Linha 20-Rosa is a separate matter
Diário do Transporte also reported that a public hearing at the Câmara Municipal on the Metrô expansion took place on 17 November. The Conselho Participativo coordinator, Carla Vidal, asked for clarification on the Linha 20-Rosa project and its impact on Largo da Batata. Residents and organizations asked about timelines, accessibility of future stations and integration with buses. According to the Câmara, representatives of the Metrô and the concessionaires did not attend.
The Linha 20-Rosa is not part of the Beco do Batman works. Diário do Transporte reported on 5 November that the Metrô had presented the Consórcio Intermunicipal Grande ABC a plan to start building the line in 2028, beginning in Santo André. The project covers about 33 km and 24 stations up to the Santa Marina area in Lapa, in São Paulo. The Rua Medeiros de Albuquerque permit concerns only the worksite and does not change the line's route or schedule.