According to The Times of India, six Chennai Metro stations between Vadapalani and Porur may be ready by early 2027, but passenger services may not begin before June. The delay is linked to trials that Chennai Metro Rail Ltd (CMRL) must complete for automated train operation across the full stretch from Vadapalani to Poonamallee Bypass.
Which stations are affected
The 14.64 km Poonamallee Bypass–Vadapalani section of Phase 2's Corridor 4 opened on October 11, 2026. Six stations on that stretch remained closed because construction was incomplete: Alapakkam Junction, Karambakkam, Valasaravakkam, Alwarthirunagar, Saligramam Warehouse and Saligramam. Four of them are on the double-decker section that links Corridors 4 and 5 of the 118.9 km Phase 2 network.
What must happen before opening
Officials told The Times of India that work on the entry structures and facades was under way, with civil works expected to be completed in January or February 2027. The stations can open only once trains run at least in Automatic Train Operation (ATO) mode and the Commissioner of Metro Railway Safety (CMRS) gives safety clearance.
- In ATO mode, train movements are automated, but an operator remains present.
- CMRS will inspect passenger amenities at the six stations but will not accept trains run in manual mode.
- A CMRL official expects operation in UTO mode only by June or July 2027.
Impact on passengers
Officials said civil work slowed down on the double-decker section after train operations began. Passengers are waiting for the stations to open. M Shankaran, a Saligramam resident quoted by The Times of India, said that reaching a station in his area would take barely five minutes, compared with the 20 minutes he now spends travelling to Vadapalani during peak hours.
According to the report, these timelines depend on the trial and safety clearance process and may change.