Bengaluru's Namma Metro has started trial runs on the Phase 2A section of its Blue Line, running from KR Puram towards Doddanekundi metro station, according to The Times of India. The work is presented as a key step toward bringing Metro service to the Outer Ring Road (ORR), one of the city's most congested corridors.
Greater Bengaluru development minister Krishna Byre Gowda said trials had started at the first four stations of the corridor and would be extended to more stations in the coming weeks. He inspected the trial run at Doddanekkundi metro station. According to the minister, the ORR is a major employment and mobility corridor, with an estimated 11-12 lakh people working along the stretch.
Phase 2A timeline
The 19-km Phase 2A corridor runs from KR Puram to Central Silk Board and has 13 stations. Testing is expected to continue through this month, and trials are likely to reach another four stations next month, according to the report.
The minister said installation of the automatic signalling system is still pending and is targeted for completion over the next two to three months. Once signalling is finished, the mandatory safety certification process will begin. The government aims to complete signalling by January and start certification after February. Including testing and certification, the corridor is expected to need another seven to eight months before public use. The state is targeting an opening for public operations by the middle of next year.
Full Blue Line
The government has directed officials to speed up Phase 2B, particularly the KR Puram to Hebbal stretch, where construction progress needs to be strengthened. According to the minister, the full 58.2-km Blue Line will run from Central Silk Board to Kempegowda International Airport via KR Puram and Hebbal, and the government aims to complete the entire corridor within about one and a half years.
Funding and other projects
Byre Gowda said the state was working to ensure funding constraints do not slow ongoing projects. He noted that a weaker rupee had raised the loan repayment burden, and that the state was also supporting the Metro corporation's operating losses. According to the report, the Metro corporation records an annual loss of around Rs 600-700 crore including depreciation. The minister said no decision has been taken on raising fares.
The state has also discussed its Red Line proposal with the Union government, though final approval is still awaited. A double-decker corridor from Sarjapur through Ibbalur Junction to St John's has been proposed to the Centre to address traffic on Sarjapur Road.