According to Governo da Bahia — SECOM, progress on the extension of Salvador's metro Line 1 to Campo Grande was presented to the Bahia state legislature. The update was given during a meeting of the Infrastructure, Economic Development and Tourism Committee of the Legislative Assembly of Bahia (ALBA), where lawmakers also received information on the Salvador-Itaparica Bridge and the Salvador light rail (VLT).
Line 1 extension: Tramo IV
The section, called Tramo IV, extends the system between Lapa and Campo Grande. According to the source, it includes 1.06 kilometre of underground route, one new station and two ventilation shafts. The investment is R$ 2.154 billion.
The source lists the following work fronts:
- Poço São Raimundo, where excavation had reached 78% of completion.
- Poço Santa Rita, where works have started.
- Archaeological excavations in the area of the future Campo Grande station, followed by IPHAN.
The project also includes the purchase of ten new trains, with an investment of R$ 632.7 million.
Related projects in the same presentation
Governo da Bahia also reported on the VLT de Salvador. The source says the system will have 43.33 kilometres of route and 50 stops, with three integrations with the metro at Águas Claras, Bairro da Paz and Retiro. It currently operates 10.7 kilometres between São Joaquim and Ara Ketu, with 11 stops, including Estação Calçada, which was reopened on 17 June 2026. According to the source, R$ 1.91 billion has been disbursed in civil works and energy systems over 28 months.
On the Salvador-Itaparica Bridge, the source says contractors have mobilised construction sites and are building a Provisional Linear Platform and the structures needed for the central span. Officials stated that the contract was made viable again through a contractual amendment signed in June 2025.
The information comes from the state government's own release and has not been independently verified. The source does not give a new opening date for the Line 1 extension.