According to Diário do Transporte, the São Paulo city government has recognized that the metro operator Metrô met environmental obligations linked to the construction of three stations on Line 17-Ouro, the monorail that serves the south of the city and links Congonhas Airport to the rail network. The certificate was published in the Official Gazette of the municipality on 25 November 2026.
What the compensation covers
The stations concerned are Vereador José Diniz, Brooklin Paulista and Aeroporto de Congonhas. The measures included planting 411 seedlings in different parts of the city, preserving and transplanting existing trees, and making payments to the Special Fund for the Environment and Sustainable Development (FEMA).
Of the seedlings, 355 were planted in the area covered by the project, and 56 were planted in the Parque Natural Municipal Fazenda do Carmo, in the east of the city, to compensate for work in a 343.33 square metre Permanent Preservation Area. According to the publication, trees that were preserved or transplanted but did not survive were replaced either with new plantings or with payments to the municipal environmental fund.
Payments and ongoing maintenance
The certificate lists four payments that add up to R$ 216,315.29. A subtotal of R$ 134,502.39 corresponds to the last two of them.
The provisional receipt does not end all of Metrô's responsibilities. Metrô must keep maintaining the trees planted at Parque Fazenda do Carmo until 23 December 2026. The final date for maintaining the internal plantings will be confirmed by the municipal technical staff. Officials had assessed the project in an evaluation dated 23 October 2026 and issued a technical certificate after an inspection on 6 November.
Line 17-Ouro service
The first phase of Line 17-Ouro, completed on 30 June 2026 with the opening of Washington Luís station, received R$ 5.9 billion in investment, according to the São Paulo State Government. The line has 6.7 kilometres of operational track and eight stations, and it is expected to carry about 100,000 passengers a day once fully operational.
The line connects with Line 5-Lilás at Campo Belo station and with Line 9-Esmeralda at Morumbi station. Aeroporto de Congonhas station is integrated with the airport terminal through an underground passage.
Service was extended on 30 September 2026. According to Metrô, the transitional operation currently runs Monday to Saturday, from 6am to 10pm.