According to Diário do Transporte, Brazil's National Electric Energy Agency (ANEEL) formed a majority on 17 November 2026 to recommend ending the early concession of Enel Distribuição São Paulo. The final vote was postponed for a second time after director Sandoval Feitosa asked for more time to review the case. The recommendation still has to be concluded by the agency's board, and the decision on whether to end the contract rests with the Ministry of Mines and Energy. Enel would continue distributing electricity in the capital and 23 other municipalities of the metropolitan region in the meantime.
Effects on bus, metro and train services
The report links repeated power supply failures to delays in São Paulo's transit. In March 2025, Mayor Ricardo Nunes said about 80 electric buses were ready but could not enter service because garages lacked power for charging. At the MobiBrasil garage in Jabaquara, Diário do Transporte found that only eight of 33 electric buses could run with the charging capacity available. Enel said it was within the agreed timeline, while MobiBrasil disputed that account.
Rail operations were also affected. On 29 September 2025, according to CPTM, Line 10-Turquesa ran with reduced speed and longer intervals between Palmeiras-Barra Funda and Rio Grande da Serra, from 17:55 to 19:52, and the Expresso Linha 10 service was temporarily suspended. CPTM attributed the disruption to a lack of external power. On 2 October, the Metrô blamed Enel for a supply failure at the Canindé substation, which led to speed restrictions and longer intervals on Lines 1-Azul and 3-Vermelha between 7:45 and 8:30, during the morning peak.
BRT-ABC corridor
The operator of the BRT-ABC, Next Mobilidade, said that relocating poles and wiring owned by Enel held up civil works on several sections. According to the company, relocation took 455 days on Rua Abrahão Braga, 428 days at Praça dos Andarilhos and 421 days on Rua do Grito. These figures are execution periods reported by Next, not the total delay to the corridor schedule. Next also cites environmental licensing, land expropriation and road adjustments among the causes of delay. The 17.3-kilometre corridor is planned to link São Bernardo do Campo, Santo André, São Caetano do Sul and São Paulo, with integration at Tamanduateí to Line 2-Verde of the Metrô and Line 10-Turquesa of CPTM. Artesp, according to the report, considers the contractual deadline of 30 November 2024 missed and opened a process in October that could lead to the end of Next's concession.