São Paulo Metro has extended the execution deadline for civil works under Lot 3 of the Line 2-Green expansion, according to Diário do Transporte. The period moves from 27 November 2026 to 11 August 2027, roughly eight and a half months more.
According to the same publisher, the tenth amendment was signed on 17 November and published in the state Official Gazette on Monday, 23 November. It also extends the contract's validity until 11 March 2028 and requires the consortium to present a revised works schedule within 30 days. The document states that no new financial amount is added.
What Lot 3 covers
Lot 3 covers rough construction between Orfanato and Santa Clara, a section previously called Água Rasa. It includes a tunnel built with the NATM method, the New Austrian Tunneling Method, and structures linked to the Falchi Gianini ventilation and emergency exit shaft.
The contract is held by a consortium led by Mendes Junior Trading e Engenharia, with PowerChina Brasil Construtora and PowerChina International Group Limited do Brasil. The contract lists Mendes Junior as being under judicial recovery.
Two different deadlines
Diário do Transporte reports that the amendment changed two dates. The execution deadline is the period for carrying out the contracted services. The contract validity also covers administrative obligations and procedures tied to the agreement. Validity previously ended on 27 June 2027.
The amendment also replaces the project's milestone schedule annex, moving from revision 4 to revision 5.
What it means for passengers
Line 2-Green currently runs between Vila Madalena and Vila Prudente. The eastward expansion includes eight new stations up to Penha: Orfanato, Santa Clara, Anália Franco, Vila Formosa, Santa Isabel, Guilherme Giorgi, Aricanduva and Penha. At Penha, the project provides integration with Line 3-Red.
According to Diário do Transporte, earlier government planning foresees progressive opening, with a first stage reaching Vila Formosa and later arrival at Penha. The civil works deadline does not necessarily match the date a station can receive passengers, since finishing work, systems installation, tests, safety procedures and operating authorizations come first. The new document only addresses Lot 3 deadlines and does not set a new opening calendar for the whole line.