According to Gestión, Peru's Minister of Transport and Communications, Angello Tangherlini, outlined the next steps for Line 2 of the Lima Metro in an interview at CADE Ejecutivos 2026. He said difficulties on both the State and concessionaire sides have left the line without an agreed timetable.
Addendum and first stage
The government is working on an addendum to the contract. Its first step would put into operation the three stations on the Ate side. Five stations currently run between the Santa Anita market and the Evitamiento-Santa Anita bridge. With the three additional stations, about nine kilometres would operate by the second half of 2027, which the minister said would benefit 600,000 people.
Revised timetable
The addendum is expected to include a new timetable, which will reflect technical changes still needed on the pending works. According to Gestión, stations from the San Juan de Dios clinic to the Óvalo Bolognesi could open at the end of 2028 or early 2029. The full line is targeted for 2030, possibly earlier.
Arbitration and debt
The concessionaire started two arbitrations, in 2017 and 2021, over late handover of land. According to Gestión, the company won the first in 2024, but the State managed to suspend its enforcement. The second is still pending before ICSID. The minister said an initial amount of about US$37 million has partly gone to annulment, and an award of roughly US$150 million owed by the concessionaire is expected around December.
Interchange with Line 1
The concessionaire had proposed two options: an interchange at 28 de Julio station with infrastructure on the viaduct, or a functional interconnection without that station. According to Gestión, the government is aiming for an interchange building that connects Lines 1 and 2 outside the viaduct.
Lines 3 and 4
According to Gestión, the ATU signed an agreement with ProInversión in July. A project management office was planned, but a budget reallocation linked to El Niño left the ATU without funds for it. ProInversión will carry out a preliminary phase with its own budget, and an announcement on financing is expected in the first quarter of 2027.
The Pariachi tunnel, part of the Nueva Cartera Central, has a contract in progress but no budget yet. The minister said a supplementary credit linked to an anti-cyclical policy is planned for January, with works expected to start by the end of the first quarter of 2027. The first section costs more than S/ 1,000 million, within a total project valued at over S/ 20,000 million.