According to El Comercio, sections of Venezuela Avenue in Lima remain closed to traffic because of construction on Line 2 of the Lima Metro. The restrictions affect the Elio (E-08), La Alborada (E-09) and Tingo María (E-10) stations and have been in place since 27 March 2023. The source notes that the closures were originally announced to last about three and a half years, a period it says ended in September.
Aerial images taken on 17 November, which El Comercio analyzed, show asphalted and marked lanes that are still fenced off. The footage was first shared by Aarón Ballesteros, creator of the channel El Zar de los Ferrocarriles.
La Alborada
A staircase and an elevator have been built over part of Roberto Thorndike street, next to a fuel station. The images show that these structures occupy space that previously carried two-way traffic. Ballesteros said that ProInversión plans published in 2014 already included access points on road shoulders.
Metro de Lima Línea 2 S.A. told El Comercio that these structures form the north access of La Alborada and follow the approved Estudio Definitivo de Ingeniería. The company said it does not acquire land and that the grantor defines the station location.
Tingo María and Elio
At Tingo María, the images show new pavement and pedestrian crossings behind fences, close to a Makro store where a construction camp occupies part of the area. Urbanist José Carlos Soldevilla said some of these spaces might be physically ready and that the delay could be administrative, such as pending reception procedures. The company said its site team has not identified the cracks reported in the new pavement and will check whether they lie outside the fenced area. It also confirmed that the approved design does not include covers over the escalators at this station.
At Elio, vehicles use both sides of Venezuela Avenue while a central area stays fenced for work and material storage. The company said these spaces are still needed for backfilling, track superstructure installation and subcontractor camps.
Outlook and responsibilities
The company stated that part of Venezuela Avenue could reopen towards the end of 2026, subject to instructions from the grantor and signing of the relevant documents. It added that road openings are planned in stages. In early November, about 110 metres of the avenue between Manuel Tellería and Guillermo Geraldino were reported as recovered.
According to the company, decisions on the station location and on partial reopening rest with the Ministry of Transport and Communications (MTC), as grantor. El Comercio said it has sent its questions to the ministry about the criteria used for the Roberto Thorndike changes and the conditions needed to reopen the avenue to traffic.