The Light Rail Transit Authority (LRTA) in Manila, according to LRTA, plans to procure additional air-conditioning units for LRT Line 2 trains in 2027. The stated aim is to improve reliability and give passengers a more comfortable commute.

Eight spare units in the 2027 plan

According to LRTA, the procurement of eight brand-new air-conditioning units (ACUs) is included in its 2027 Annual Procurement Plan. The units will serve as rotational spares. They can be installed quickly to replace defective ACUs while the removed units are repaired or reconditioned. The procurement is at an early stage under Purchase Request No. RS2-2701-005.

Why the change is needed

LRTA Administrator Hernando T. Cabrera said the plan is part of LRTA's continuing work to keep train air-conditioning reliable. He pointed to the long operating hours of the units. According to Cabrera, the train air-conditioning units have run for up to 20 hours a day over the past seven years, which has worn down the equipment and its components.

Stricter maintenance schedule

LRTA has also changed its ACU maintenance program to catch problems earlier, according to the authority:

  • Fresh and return air filters are now cleaned weekly, up from monthly.
  • Condenser and evaporator coils, drain holes and dust-block mesh plates are cleaned monthly, up from quarterly.
  • User interface program testing and refrigerant flow inspection are carried out monthly.
  • Impeller fans are cleaned quarterly instead of semi-annually.

Some extra ACU cleaning is done during off-peak hours to follow the revised schedule.

Earlier purchase and budget plans

In 2025, LRTA procured eight brand-new ACUs under Purchase Request No. RS-2401-044. According to the authority, these were delivered on September 19, 2025, to provide ready replacements for defective equipment.

The rehabilitation of the train air-conditioning system is included in LRTA's 2027 budget proposal under Tier 2 funding. LRTA is also recommending the systematic replacement of ACUs on its ten trainsets. The first systematic replacement was completed on May 4, 2019.

According to the information released by LRTA, these measures together aim to improve cooling performance, reduce unscheduled maintenance and limit service disruptions on LRT Line 2.